User Interface Standard Lead Times, Samples, & Production Parts
Below you will find our standard lead times for all our user interfaces products. You will also find our standard lead times for manufacturing pre-production engineering, product samples, and production parts.
SMART User Interfaces
- Design & Development Phase: 40-60 working days
- Dependent on complexity of electrical/firmware requirements
- Samples: 30 working days
- Production parts: 30-40 working days
- Dependent on quantity and material lead times
Membrane Switches
- Pre-production engineering: 3-5 working days
- Samples: 25 working days
- Production parts: 25 working days
Silicone Rubber Keypads
- Pre-production engineering: 3-5 working days
- Samples: 25 working days
- Production parts: 25 working days
Graphic Overlays
- Pre-production engineering: 2-4 working days
- Samples: 25 working days
- Production parts: 25 working days
Need Precision and Speed for Your Next HMI Project?
From samples to production, we will ensure your HMI project moves through manufacturing based on the lead times you need. Don't miss your project deadline, act now!