SMART User Interfaces

  • Design & Development Phase: 40-60 working days
    • Dependent on complexity of electrical/firmware requirements
    • Samples: 30 working days
    • Production parts: 30-40 working days
      • Dependent on quantity and material lead times

SMART User Interfac


Membrane Switches

  • Pre-production engineering: 3-5 working days
  • Samples: 25 working days
  • Production parts: 25 working days

Membrane Switch


Silicone Rubber Keypads

  • Pre-production engineering: 3-5 working days
  • Samples: 25 working days
  • Production parts: 25 working days

Silicone Rubber Keypad


Graphic Overlays

  • Pre-production engineering: 2-4 working days
  • Samples: 25 working days
  • Production parts: 25 working days

Graphic Overlay

Celebrating 65 Years of Manufacturing Excellence  Learn More →
America's Oldest. A History of Innovation.

Today at Epec, the customer comes first, and everything we do must be put through that filter. Whether it is developing e-commerce platforms to make it easier to work with us, or creating a NPI (new product introduction) process that helps our customers get to market faster, or the other 10 new projects we have in process, we must focus on building the new. By doing that every day, and by always making the customer our top priority, we plan on being here for another 65 years and then some.

Learn more about our 65 year story →



Celebrating 65 Years - Epec Engineered Technologies